A useful stone-sculpture specification separates what is known at enquiry from what must be approved before production, dispatch and installation. Use the checklist below as a project record, not as a substitute for the contract, structural design, lifting plan, planning advice or customs declaration.
For every field, mark:
- P — provisional and allowed to change;
- F — fixed by an identified approval;
- N/A — not applicable, with a reason; or
- TBC — owner and due date recorded.
RIBA's Plan of Work uses staged outcomes and information exchanges to stop decisions being fixed at the wrong time.1 This checklist adapts that discipline to a standalone sculpture; it does not claim that a sculpture commission is itself a RIBA building project.
A. Enquiry and comparable-quotation checklist
Purpose and scope
- Project and piece identifier
- Intended use and desired response
- Quantity and whether units should match, mirror or vary
- Interior, sheltered or exposed setting
- Sculpture-only, delivered or installed quotation boundary
- Client, designer and decision-maker contacts
- Budget basis and tax status
- Desired completion date and any genuinely fixed dates
Site and context
- Site address and jurisdiction
- Main viewing directions and distances
- Site photographs with date and viewpoint
- Existing building, landscape, wall, pier, plinth or slab information
- Planning, conservation-area, listed-building or registered-landscape context
- Public access, foreseeable contact and security considerations
- Weather, irrigation, salt, pollution and water-collection exposure
- Inspection and maintenance access
In England, listed-building consent is distinct from planning permission, and works affecting a listed building's character require consent; designated historic landscapes are also considered through the planning system.2 Confirm the actual position with the relevant authority. Scotland, Wales and Northern Ireland have different legislation and bodies.
Geometry and references
- Approximate overall H × W × D in millimetres
- Maximum envelope and minimum clearances
- Preferred orientation and pose
- Required inscriptions, emblems or applied elements
- Reference images labelled inspiration, requirement or do not copy
- Reference hierarchy stating which document governs
- Known copyright owner and permission status for each third-party reference
Commissioning a work does not automatically transfer copyright. GOV.UK guidance says the creator is normally the first owner unless otherwise agreed in writing.3 Record licences, reproduction, photography, credit, alterations and future-copy rights in the contract.
Information required with the quotation
- Assumptions and exclusions
- Design-stage deliverables and revision allowance
- Proposed material route and stated limitations
- Samples, models or prototypes included
- Production, packing, delivery and installation boundaries
- Information required from the client or project team
- Quotation validity and change-control basis
- Proposed approval and payment milestones
Do not compare headline prices until these boundaries match.
B. Design and pre-production checklist
Approved design information
- Drawing, model or maquette identifier and revision
- Overall and critical dimensions
- Unit breakdown and joint locations
- Datum, orientation and setting-out points
- Visual priority areas and intentionally simplified areas
- Agreed project tolerances — no universal carving tolerance assumed
- Conflict rule between drawing, model, render and sample
- Named approver and dated approval
An approved render does not approve an unseen fixing, joint, tolerance or natural-stone marking.
Stone identity and evidence
- Geological and commercial name
- Quarry or mine, country of origin and bed where applicable
- Proposed block or supply reference
- Relevant current test information and its relation to the proposed supply
- Indicative sample
- Representative range/control reference
- Finish sample made by the proposed method
- Expected natural features and agreed acceptance range
- Bedding or grain orientation marked where relevant
- Substitution process
BGS defines dimension stone by geological source and use, and its laboratories test properties including density, porosity, water absorption and strength.45 The project team should identify which evidence is relevant; this checklist supplies no generic pass value.
Stone Federation GB recommends range or control panels that show the expected geological characteristics of a selected bed or available blocks.6 A small colour chip is therefore an indicative reference, not a promise that every surface will be identical.
Interfaces and responsibilities
- Confirmed sculpture and base mass
- Base footprint and bearing surface
- Centre-of-gravity information where available
- Holes, sockets, dowels or other interfaces shown
- Foundation designer
- Structural and fixing designer
- Existing-structure survey owner
- Installer and setting-out owner
- Temporary-works responsibility
- Information issue dates between supplier, engineer and installer
The sculpture drawing should coordinate with the engineer's design; it should not be mistaken for that design.
Production release
- All approval documents listed by identifier and revision
- Open items either closed or expressly accepted as provisional
- Material and finish approvals signed
- Change process, authority and cost/programme treatment agreed
- Progress evidence and inspection points agreed
- Non-conformity and disposition route agreed
- Production release signed and dated
C. Pre-dispatch checklist
Identity, dimensions and condition
- Piece ID and approved revision
- Key actual dimensions recorded
- Unit count and joint match checked
- Finish checked against the approved reference
- Required views photographed with scale and date
- Visible condition and accepted natural features recorded
- Interfaces, orientation marks and loose components checked
- Exceptions recorded with disposition and approval
Packing and shipment
- Crate ID, contents and unit-to-crate map
- Net and gross mass
- External crate dimensions
- Lifting, fork-entry and centre-of-gravity markings where applicable
- Protection and restraint record
- Packing photographs
- Shipping marks and delivery contact
- Insurance and transit-risk point confirmed in the contract
For solid wood packaging entering Great Britain from another country, GOV.UK requires ISPM 15-compliant material and a legible mark; a certificate does not replace the mark. Northern Ireland rules differ.7
Imports, where applicable
- Importer and declarant identified
- Appropriate EORI confirmed
- Commodity code confirmed for the actual goods
- Customs value and origin evidence
- Licence, certificate or restriction check
- Duty, VAT and clearance responsibility
- Commercial invoice and packing list
GOV.UK's import process requires the importer to address EORI, commodity code, value, licences or certificates, declaration and record-keeping.8 This checklist deliberately gives no fixed commodity code or duty rate.
D. Delivery, installation and handover checklist
Site readiness and lifting
- Delivery vehicle and route checked
- Gate widths, turning and unloading position checked
- Ground and slab capacity confirmed by the responsible party
- Exclusion zones and public protection planned
- Suitable lifting points or approved handling method
- Lift planner, supervisor and competent operators appointed
- Equipment capacity and examination records checked
- Weather limits and stop criteria set
- Installation sequence and temporary stability addressed
HSE states that lifting operations involving lifting equipment must be planned by a competent person, appropriately supervised and carried out safely.9 Mass, dimensions and interface data from the sculpture supplier are inputs to that plan, not the plan itself.
Handover
- Condition on arrival recorded before unpacking and after installation
- Installation and fixing records supplied by the responsible parties
- As-built information and final mass/unit schedule
- Material and finish record
- Inspection, cleaning and maintenance guidance
- Limitations and escalation contacts
- Copyright, photography and credit permissions
- Contractual certificates or warranties actually due
- Owner and date for the first inspection
Responsibility schedule
Do not leave a risky item under "by others". Name one lead party and the information it needs.
| Item | Lead party | Input required | Approval or record |
|---|---|---|---|
| Design intent | Client/designer | Brief and references | Design approval |
| Stone and finish | Designer/material adviser | Source evidence and range samples | Material approval |
| Foundation and fixing | Structural engineer | Mass, interfaces and site survey | Engineer's design |
| Permissions | Client/planning adviser | Site and proposal information | Decision or written advice |
| Packing and transport | Contract-named party | Unit/crate schedule and route | Packing/shipping record |
| Lifting and installation | Competent lift/installation team | Mass, centre of gravity, interfaces and site | Lift plan and installation record |
| Inspection and care | Owner/facilities lead | Handover guidance | Inspection log |
Final issue check
Before issuing the specification, confirm that:
- every factual requirement has an owner;
- every approval names a document and revision;
- every provisional item has a due date;
- material appearance and technical evidence are separate approvals;
- design approval does not waive rights or hidden defects;
- customs and lifting duties are not assigned by assumption; and
- the contract, drawings, samples and responsibility schedule do not contradict one another.
The checklist is ready to copy into a project document. Adapt it to the contract, procurement route, jurisdiction, site and risk; delete nothing merely to make the brief look complete.
Sources
All sources accessed 20 July 2026.
Footnotes
-
Royal Institute of British Architects, RIBA Plan of Work. ↩
-
Department for Levelling Up, Housing and Communities and Ministry of Housing, Communities & Local Government, GOV.UK, Conserving and enhancing the historic environment. ↩
-
Intellectual Property Office, GOV.UK, Ownership of copyright works. ↩
-
British Geological Survey, MineralsUK, Building Stones Database for Scotland. ↩
-
British Geological Survey, MineralsUK, Stone collections, data and testing. ↩
-
Stone Federation GB, Stone sample panels — what you should be looking for. ↩
-
Forestry Commission, GOV.UK, Wood packaging material for import and export. ↩
-
GOV.UK, Import goods into the UK: step by step. ↩
-
Health and Safety Executive, Lifting operations. ↩